Benton County

Size:
112 kW
Installed:
December 2020

The Oregon Clean Power Co-op will install a 112 kW solar system at Benton County’s building at 4500 SW Research Way, in Corvallis. The County purchased the building in 2020, and aims to move it as close as possible to net-zero energy.

The project is fully funded, with financing from investment by community members, the Energy Trust of Oregon, tax credits taken by a third-party investor, and the County itself.

Construction on the project was completed in December 2020.

Benton County Offering Memorandum

Benton County Investment Summary

Benton County Investment Process